PSAM Bamberg Large-Scale Storage Facility

Challenge
Building a high-performance energy infrastructure required the coordinated implementation of numerous trades—from the construction of the station building to medium- and low-voltage systems, and the integration of transformers and power units. At the same time, all interfaces between the system components, as well as the commissioning process involving multiple project partners, had to be reliably coordinated.
Solution
By providing turnkey implementation of the entire electrical infrastructure from a single source, all system components could be optimally coordinated with one another. From planning and the installation of medium- and low-voltage systems to cabling, the transformer station, and commissioning, a high-performance and reliable power supply solution was created.
Location
Bamberg
Pixii Germany GmbH
Key Facts
- Planning, design, and construction of the substation building, including raised floors and a lightning protection system
- Planning, construction, and installation of the low-voltage system
- Planning and installation of the medium-voltage system
- Substation outfitting, including cable routes, cable trays, and lighting
- Cable connection and wiring of the power units
- Installation and connection of the transformers
- Connection of the MV and LV cables to the respective distribution panels, including all control and signaling lines
- Commissioning of the substation on both the MV and LV sides in collaboration with two partner companies